Three-point estimation

Split tasks in its minimum definition and estimate those minimum tasks by Optimistic (O) - Most Likely (M) - Pessimistic (P).

With those estimations we do PERT distribution and then add those estimations

(O+(4xM)+P)/6

Example

Task: Migrate x database Minimum tasks:

  • migrate service 1 to y database
  • migrate service 2 to y database
  • migrate connector to use y database
  • test changes in test env

Then we estimate those tasks

task Optimistic Most likely Pessimistic PERT Comments
migrate service 1 10h 25h 55h 28h (I round hours up)
migrate service 2 4h 14h 22h 14h take x into account
migrate connector 20h 40h 80h 44h  
test changes 2h 7h 14h 8h  
total estimation for task       94h  